Cabinet Committee on Economic Affairs (CCEA) today approved the execution of Kameng Hydro Electric Project (600 MW) in Arunachal Pradesh by North Eastern Electric Power Corporation Ltd. (NEEPCO) at an estimated cost of Rs.2496.90 crore including Interest During Construction (IDC) component of Rs.249.09 crore considering the rate of interest on loan component.
The power generated from this project would be allocated to the various beneficiary states of the North Eastern Region and supplied as per Power Purchase Agreements.
The Kameng Hydro Electric Project (600 MW) is located in the West Kameng district of Arunachal Pradesh in the North Eastern Region. The Project is planned as a run-of-river scheme, utilizing the flows of Bichom and Tenga Rivers (tributaries of the Kameng River).
|