transmission system of power grid corporation

Thursday, May 26, 2005

The Cabinet Committee on Economic Affairs (CCEA) today gave its approval for the establishment of transmission system associated with Rajasthan Atomic Power Project (RAPP) – 5 & 6 at a total estimated cost of Rs.499.45 crore including an IDC (Interest During Construction) component of Rs.22.38 crore (at 4th quarter, 2004 price level). The approved transmission lines are:


(i) RAPP – Kankroli 400 kV Double Circuit (D/C) transmission line – 198 Km

(ii) RAPP – Kota 400 kV Single Circuit (S/C) transmission line – 62 Km


The transmission system is likely to be completed within 33 months.


The transmission project would facilitate evacuation of power from Rajasthan Atomic Power Project (RAPP) – 5 & 6 and further dispersal to various beneficiaries of Northern Region. Power Grid will complete the system in a manner that when Atomic Power Unit will be commissioned in June’ 2007, the transmission system will be available. The beneficiary States will be all Northern States, viz., J&K, Rajasthan, Punjab, Haryana, U.P., Uttaranchal & Delhi.


RK:DS:LV