Cabinet Committee on Economic Affairs today gave its approval for construction of Transmission System associated with Kahalgaon Stage-II, Phase-II (1 x 500 MW) Project at total estimated cost of Rs.464.02 crore including an IDC Component (Interest During Construction) of Rs.28.98 crore. The project would be completed within 33 months once started.
NTPC is augmenting Kahalgaon Stage-I project (4 x 210 MW) located in Bihar (Eastern Region) by another 1500 MW in two phases (Phase-I, 2 x 500 MW) and (Phase-II, 1 x 500 MW) under stage-II. This transmission project would facilitate evacuation of power from Kahalgaon Stage-II, Phase-II generation project and its further dispersal to various beneficiaries.
|