It is proposed to construct a tunnel at Rohtang to provide an all weather road to Leh.
In May 2002 it was decided as a first step to construct approach roads to both the North and South portals of the proposed tunnel at Rohtang at a cost of Rs 30 crore. Two approach roads were to be constructed of 2.7 kms (South portal) and 23.8 kms (North portal ). The approach road to the South portal and 23.46 kms of the approach road to the North portal has been completed.
A sum of Rs 30 crore has been utilized till March 2004. The amount spent during the current financial year is Rs. 14.82 crore in addition. Because of limited working season no further expenditure is anticipated in this financial year.
On the basis of Detailed Project Report prepared by M/s Rail India Technical & Economic Services (RITES) the estimated cost of Rohtang Tunnel and other related works is Rs 1709.35 crore. The work relating to construction of approach roads and alternate route to Leh is already under progress by the Border Roads Organisation and construction of tunnel will be taken up through a contractor for which global tenders would be invited.
Construction of tunnel and other related works will provide strategic operational support to the Army and lead to economic development of the area. This will also reduce the distance between Manali and Leh by 40 km.
The work relating to construction of tunnel and other related works is proposed to be completed by 2011-2012.
This information was given by the Defence Minister Shri Pranab Mukherjee in a written reply to Dr Col (Retd) Dhani Ram Shandil in Lok Sabha today.
|